Weekly Activities

October 19, 2015: Posillico, National Grid’s Remediation Contractor, has continued mobilization which includes delivery of equipment for remediation activities. Posillico has closed a portion of the shoulder on the north side of Beach Channel Drive using concrete barriers. Construction signs warning of the shoulder closure have also been put in place. Posillico has also started leveling the bulkhead area so that the machines can site level while performing the remedial activities.

For the week of October 26, 2015, Posillico will continue to grade work zone within the bulkhead area and will begin to uncover the tunnel that had connected the bulkhead area to the main Former MGP site. The tunnel will then be inspected for stability and filled in if necessary.