Weekly Update Ending: July 02, 2010
![]() Tent Position #15 Load Out |
National Grid’s Remediation Contractor continued with site remediation activities, which included the delivery of construction materials, imported backfill material (stone and common fill), as well as construction equipment and supplies. On-site Waterloo BarrierTM interlocking steel sheet piling flushing and grouting operations continued. Tent Position #15 Shallow Excavation activities continued with off-site transport and disposal of impacted soils at approved and permitted disposal facilities. Common fill material deliveries and final grading and cap installation activities continued to progress in the central and eastern parts of the Site. National Grid’s consulting engineer conducted noise and vibration monitoring activities, as necessary.
Maintenance of the decontamination areas, work zones, on-site gravel access roads, parking areas and material staging areas, imported backfill material (i.e., clean fill), stockpile covers, the perimeter privacy screen, and soil erosion and sediment control (SESC) measures continued. Odor and dust suppression activities were conducted, as necessary. National Grid’s consulting engineers continued to monitor the site activities with the community air monitoring program (CAMP) equipment.
![]() Tent Position#15 |
During the period from June 28, 2010 through July 4, 2010, six fixed base CAMP units and two portable CAMP units were in-use and measured total volatile organic compounds (TVOC) and particulates (PM10). Fifteen-minute averages for both TVOC and PM10 data remained in the Operational Condition. On Monday, June 28, 2010 and Tuesday, June 29, 2010, periods of elevated PM10 concentrations at Fixed Air Monitoring Site 1 (FAM 1) were measured and were attributable to high relative humidity. On Tuesday, June 29, 2010, elevated PM10 concentrations were attributable to exhaust from a generator in the vicinity of FAM 1 as well as high relative humidity. All elevated concentrations were reduced below the Action Limit after background subtraction.. The Weekly Report that summarizes the CAMP data can be found as a separate tab in the Weekly Report Archive section.
For the holiday week of July 6, 2010 through July 9, 2010, Cap material deliveries along with final grading and Cap installation activities are scheduled to continue in the central and eastern part of the Site. Tent Position #15 Shallow Excavation activities are scheduled to continue with off-site transport and disposal of impacted soils at approved and permitted disposal facilities. Flushing and grouting operations of the on-site Waterloo BarrierTM interlocking steel sheet piling are scheduled to be completed. Odor and dust suppression activities will be conducted, as necessary. Work zone delineation, site maintenance activities, CAMP operation monitoring activities will continue, and noise and vibration monitoring activities will continue, as necessary.